Year of work on the project: 2021-2022
Type of work: rent of boiler equipment, delivery of equipment, installation of equipment on site, installation/dismantling of temporary heating networks, commissioning, organization of round-the-clock control post, monthly maintenance, including fuel supply and water supply.
Address: Moscow, Alexandra Monakhova str., Buninskie Luga housing complex
Task from the client: tender task to provide heat supply for the housing complex "Buninskie Luga", including integrated water supply.
Our solution: boiler houses with a total capacity of 8.42 MW have been installed with fuel storage facilities with a total volume of 10 m3 and automated water supply modules with a volume of 6 m3.